Equally distributed hourly resource allocation method

(1) ShareShare
ReportReport
Posted on by 9
I have a question about the Resource ALLOCATION METHOD in Dynamics Project Operations.  The existing methods are: None, Full Capacity, Percentage of capacity, Hourly: distribute equally, Hourly: charge in advance.
None of the previous methods fits my need, which is when I assign hours to a resource, these must be distributed equally over the days between the start and end date.  For example: if I assign a resource 10 hours between Monday, May 6 to the 10th, I want it to be assigned 2 hours during each day, 2 on Monday, May 6, 2 on Tuesday, 2 on Wednesday, 2 on Thursday and 2 on Friday 10th May.
Does anyone know and can guide me to resolve this situation?
Thank you
 
Tengo una pregunta sobre el MÉTODO DE ASIGNACIÓN de Recursos en Dynamics Project Operations.  Los métodos existentes son: Ninguno, Capacidad Plena, Porcentaje de capacidad, Por Horas: distribuir equitativamente, Por Horas: cobrar por adelantado.

Ninguno de los métodos anteriores se ajusta a mi necesidad, que es cuando asigno horas a un recurso, estas deben distribuirse equitativamente entre los días entre la fecha de inicio y finalización.  Por ejemplo: si a un recurso le asigno 10 horas entre el lunes 6 de mayo al 10, quiero que se le asigne 2 horas durante cada día, 2 el lunes 6 de mayo, 2 el martes, 2 el miércoles, 2 el jueves y 2 el viernes 10 de mayo.

¿Alguien sabe y puede orientarme para resolver esta situación?

Gracias
I have the same question (0)
  • Suggested answer
    Erica J Ellis Profile Picture
    71 on at
    Equally distributed hourly resource allocation method
    Hello,
     
    I would expect the Allocation Method of "By Hours - Distribute Evenly" to work just as you described. I tested it and it distributed 2 hours each day. Can you tell me what happens when you try that Allocation Method?
     
     
    The result - 
  • Judy Profile Picture
    3,605 Microsoft Employee on at
    Equally distributed hourly resource allocation method
    Moved to Project Operation Forum.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Mansi Soni – Community Spotlight

We are honored to recognize Mansi Soni as our August 2025 Community…

Announcing our 2025 Season 2 Super Users!

A new season of Super Users has arrived, and we are so grateful for…

Congratulations to the July Top 10 Community Leaders!

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans