Hi Estimation Gurus!

I m using D365 FO. And I have following very Crucial questions regarding Costs in Production Estimates:

1- Can i somehow manually adjust cost in Production estimate? Through Trade agreements maintenance etc?

2- I purchase project specific materials and Batch cost/PO cost for current project for which i have created this production order is different from already maintained in Inventory. Can i get specific PO or Batch cost in Production order estimate? (By marking or somw other wayout)

3- I have a Project based Production Order which can go for more than an year. Can i run re Estimate after Production is started without reversing the status. I know there is Update cost feature in Periodic processing of Production control, but it doesn't work that way.

4- What are the impacts of variance in estimated and Actual cost after production order is ended, but FG was sold in previous periods?

I have the same question (0)
  • Mubeen Faizullah Profile Picture
    139 on at
    RE: Estimating the Production Order Correctly

    Hi Dolores

    Yes its overall requirement.

    Although adjustment to estimated cost can be done through last cost price adjusment on Inventory form. or chang of cost in inventory Setup price.

  • Dolores Young Profile Picture
    on at
    RE: Estimating the Production Order Correctly

    Hi,

    I don't believe there is any way to manually adjust the estimated cost of the Production.   If 'use estimated cost' is enabled for report as finished, the goods will come into stock at the estimated cost. If they are then sold, this will be the estimated cost of the sale.  However, once you end the production order, if the actual cost is different, an inventory close or recalculation will adjust the sales cost.

    Is the requirement to re-estimate the production order related to projects?

    Regards

    Dolores

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Mansi Soni – Community Spotlight

We are honored to recognize Mansi Soni as our August 2025 Community…

Announcing our 2025 Season 2 Super Users!

A new season of Super Users has arrived, and we are so grateful for…

Congratulations to the July Top 10 Community Leaders!

These are the community rock stars!

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
SoumitraforD365 Profile Picture

SoumitraforD365 29

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 12 Super User 2025 Season 2

#3
Sagar Suman Profile Picture

Sagar Suman 4 Super User 2025 Season 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans