Release Purchase Requisition that is Over Budget

(0) ShareShare
ReportReport
Posted on by 175

Hey Everyone, 

I have run into a scenario I am looking for help with. Basically, the user wants to have budget control turned on but not be stopped by anything in the system. They just want warnings every time they are over budget in any documents (purchase requisition, purchase orders, vendor invoices, etc).

We have budget control turned on for specific main accounts. We have an over-budget user group with permission to go over budget. 

- Create a purchase requisition that is over budget

- The approval workflow gets completed so the purchase requisition is approved.

- But, now I can not release the purchase requisition. I can not do it with the batch jobs or manually.

Does anyone have a way to do this?

The end goal is the user wants to get warnings but never be stopped in their process.

Thanks!

  • 72camaross Profile Picture
    175 on at
    RE: Release Purchase Requisition that is Over Budget

    No. I think what I was trying to do is against what the system would let me.

    I have not been able to check if they are in the over-budget group that the user will move forward, but thanks for the response! I know I was in the over-budget group but couldn't get a PR to release.

  • Charlotte X Profile Picture
    on at
    RE: Release Purchase Requisition that is Over Budget

    Hi,

    Is your problem solved?

  • Suggested answer
    Charlotte X Profile Picture
    on at
    RE: Release Purchase Requisition that is Over Budget

    Hi,

    Click Budgeting > Setup > Budget control > Budget control configuration.

    Click Over budget permissions.

    In the Over budget options field, select the appropriate option for this user group.

    Allow over budget processing – Users in this group can process a budget register entry if the available budget balance is insufficient to cover the entry.

    If you are using DAX, there is a button "reserve budget funds" on PR in financial tab, you need to click for approved PR in DAX. Then it will be visible to approved PR.

    Best Regards,

    Charlotte

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Dynamics 365 Community Update – Sep 16th

Welcome to the next edition of the Community Platform Update. This is a weekly…

Announcing Our 2024 Season 2 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Dynamics 365 Community Newsletter - September 2024

Check out the latest community news

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Jahanvi Profile Picture

Jahanvi 34

#2
PJ JohnPaul Profile Picture

PJ JohnPaul 5

#3
SudhanshuMSID Profile Picture

SudhanshuMSID 1

Overall leaderboard

Product updates

Dynamics 365 release plans