Fix Price subcontracts in Project Service Quote calculation

(1) ShareShare
ReportReport
Posted on by 2

Hello, we are struggling with Fixed Price subcontracts in Project Service Quote calculation. We are unsure whether to create custom functions or if standard Project Operations functions can be used. We are currently implementing Project Operations - Lite Deployment. We are acting as a system integrator on the projects and, in addition to our own services, we are also delivering deliveries from other IT companies as part of the final solution.

  • We need to include Fixed Price subcontracts in the calculation within the Project Service Quote.
  • In the calculation, we need to consider the cost of the subcontract, the margin over it, and the contingency.
  • We have one contract with the client. The client is invoiced one amount, including our work and the subcontracts.
  • We would like to have it consistent for the subsequent Project Budget, invoice planning etc.
  • Should we enter the subcontract as a Quote Line, one of the rows in Quote Line Details, or as a Write-In product?
I have the same question (0)
  • Erica J Ellis Profile Picture
    71 on at
    Fix Price subcontracts in Project Service Quote calculation
    Hi Filip,
     
    You could build the work performed by the subcontractor into the project plan and I think it would achieve most of what you describe with standard functionality. It would look like this:
    • You have Project Tasks in your Project representing the subcontractor work. Those Project Tasks are assigned to a Project Team Member.
    • The Project Team Member is associated to the fixed fee Subcontract
    • Import the Project estimates into the Quote as Quote Line Details. I don't think you need the subcontract work on a separate Quote Line, but you could if you wanted it that way. The Quote Line Details imported for the subcontracted Project Tasks will use the Subcontract's price list to determine the cost.
    • If you build the Subcontract into the Project, then it will carry through to the budget and invoicing.
    Let me know if you have additional questions about that approach.
     
    Erica

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Mansi Soni – Community Spotlight

We are honored to recognize Mansi Soni as our August 2025 Community…

Announcing our 2025 Season 2 Super Users!

A new season of Super Users has arrived, and we are so grateful for…

Congratulations to the July Top 10 Community Leaders!

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans