Hello everyone,
I have a new issue today with purchase requisition.
What i've done:
1) i created a new service product :
2) i set the product category to the procurement herarchy :
3) I created two trades agreements :
Same amount for two vendors with different date range (simulate a change of a source vendor)
4) i defined the delivery date in the procurement parameters :
5) i activate the price :
After this setup done, i've created a new purchase requisition.
When i select my product, price and vendor are good for the current date (16/04/2020) :
If i change the requested date nothing happen :
But if i change the quantity after the date change, the price change to a wrong price (purch price of the product page) but the vendor is good :
The question are :
Why did it happend?
How to get the good price?
Hope you can help me,
Regards,
Jonnix